How We Completed the Project
Here’s the site plan detailing all the activities planned for this property, giving you a clear idea of the scope of work required for this project:
Concrete Pad Site Preparation
For the 385 sq. ft. concrete pad, we started the site preparation by excavating the area with removing the grass and the topsoil. Formed the area, Installed a base layer with 9 tons of #1 Crusher Run, graded and compacted to provide stability. Allowed the base to settle for a few weeks before pouring concrete.
Concrete Pad Site Preparation (Before, Excavate & Formworks)
Gravel Base Before Concrete Pad
Gravel Driveway Repair and Installation
We started with a thorough surface repair and preparation over the existing 2,800 sq. ft. driveway area. Delivered and installed 32 tons of #1 Crusher Run driveway stone. Applied the stones in a 2-inch thick layer, graded, compacted, and rolled to create a level surface and eliminate problem areas.
The client requested an additional 550 sq. ft. extension to create a swinging corner, allowing their truck and trailer to turn with ease. Repaired and prepared the area to ensure a solid base for the new section. Delivered and installed 13 tons of #1 Crusher Run driveway stone. Applied the stones in a 4-inch thick layer, followed by grading, compaction, and rolling to achieve a sturdy and even surface.
Gravel Driveway Needs Refresher
Gravel Driveway Needs Refresher
Here are the final results—check out the side-by-side transformation of this driveway!
The transformation after gravel driveway refresher (View from the House)
The transformation after gravel driveway refresher (View from the Shed)
The transformation after gravel driveway refresher (View from the driveway end)
Refreshed Gravel Driveway
Concrete Pad Concreting
The project kicked off with the arrival of the mixer truck. After a few weeks, we returned to deliver and pour 5 yards of 3,500 psi concrete. As the concrete flowed out, we worked quickly to scatter and spread it evenly across the area. The team ensured there were no gaps or uneven spots, carefully guiding the concrete into every corner.
With the concrete spread out, it was time for vibratory screeding. The vibrations helped settle the mix, removing air pockets and compacting the material for a uniform, stable slab.
Once the concrete had set slightly, we moved on to the finishing stage. The surface was carefully smoothed out to achieve a clean, professional look. For added safety and functionality, we applied a brush finish. The result was a durable, well-finished concrete slab ready to stand the test of time.
The result was a durable, well-finished concrete slab ready to stand the test of time.
Completed Concrete Pad in Lyndonville
Here is a video taken by our Operations Head, Daniel Colella showcasing the completed concrete pad: